微信刷题,考证常用
  • 所属考试信息系统项目管理师试题库
  • 试题题型【单项选择题】
试题内容
Since risk is associated with most projects, the best course of act is to()。
  • A.cover all project risks by buying appropriate insurance
  • B.ignore the risks ,since nothing can be done about them and move forward with the project in an expeditious manner
  • C.avoid projects with clear and present risk
  • D.identify various risks and implement actions to mitigate the potential impact
信息系统项目管理师在线题库
  • 参考答案:D
  • 解题思路: 本题题意为:在项目风险控制中,最恰当的做法是
    A意为通过购买保险覆盖所有风险。B意为无视风险,快速推进项目。C意为规避发生风险。D意为识别风险,并提供对应措施。
    根据题意,正确答案为D